The Council moved forward on the process for the 2006 Street improvements. The following time table was presented by the City Engineer:
March 29th the project is advertised for bid
April 20th the City receives bids
May 2nd The Council holds an informational meeting and awards the contract
May 15th Contractor begins work
October 13th Contractor substantially complete
October 17th Council Receives assessment rolls and orders public hearing
November 21st Public Hearing
June 2007 Construction complete
I was appointed to the Development Review Committee. I believe this Committee can act as a check to make sure development pays for itself. Each Development Agreement must be fair to the citizens of Isanti. Each developer must be treated equally giving no special treatment to anyone.
The Mayor and Council Member Larson were appointed to the School liaison positions. I will be asking that they press the School District for payment of the money owed for the School Resource Officer.
The City Engineer will have specific office hours on Tuesdays. For more information call City Hall 444-5512.
1 comment:
Good luck Getting the Mayor or Councilwoman Larson to do any of that! They will probably grant them 20,000 more thousand in "freebies". Thanks for trying George, at least you do.
Post a Comment